Remove the disconnect between PWDI & PWDM

Currently, internal reviews(using WFs) and external reviews (using PWDM) are 2 separate processes. There is no single master status on the document that reflects the live status in the project lifecycle. External communication stages shall also have status reflected in the parent document.

Practical use of functionality?

This is more important from a Project controls perspective. At any point, it shall be easy to identify what is the status of all the agreed submission documents of a project.

What is the impact of not doing this?

Now it takes effort to connect these two services and reporting is also not a straight straightforward process. This makes the tool not so popular with the PM and Controls department, and there are solutions that do this better on the market.

  • Guest
    Reply
    |
    Oct 25, 2023

    Justina

    We use this, however we have documents that are part of multiple transmittals, being reviewed by different groups of reviewers.


    The field keep only keep the last status received. If we could have a way to keep the history.

  • Guest
    Reply
    |
    Oct 19, 2023

    To add to below, the dates across these statutes (internal and external) a document version goes through are equally important from a reporting point of view for the planning and project controls team. This is the main information project management needs out of an EDMS, which can help them calculate a trustable engineering progress value figure.

  • Guest
    Reply
    |
    Oct 19, 2023

    Hi Justina,

    Two gaps with the existing approach:

    1. The status field from DM is limited to submittals. The outgoing doc status is missing.

    2. It is a separate status field as such. Quite different from PW's internal workflow status.

    From a project controls perspective: At any point, the user needs to know the current status. Internal / External reviews do not matter, it is one closed loop for users and one long list of statuses for tracking. The Project Control manager needs to know if the document finished internal WIP (3-step WF) and as of now has been sent to an external party, or is it acknowledged or responded to? if yes, then the corresponding doc status etc. in a single attribute / live report/search results page.

    Hope that helps.

    Regards,

    Arun

  • Admin
    Justina Jureviciene
    Reply
    |
    Oct 19, 2023

    Have you considered storing Deliverables Management response status as a document attribute value in ProjectWise Explorer?
    https://docs.bentley.com/LiveContent/web/ProjectWise%20Deliverables%20Management%20connector%20for%20ProjectWise-v9/en/GUID-32C2F539-A84E-4C28-87B2-F2F345E876DE.html

    Would it work for your use case?