Request is to add the possibility to set response date based on working day as oppose to calendar days. and taking into account the holidays for each regions.
Practical use of functionality?
We have the situation where we set 4 days to review but include in those four days 2 weekend days and one holliday, which left one day to response. |
|
What is the impact of not doing this?
Give false impression that we have many days to provide an answer but that is not the case |
Thank you Justina for the follow-up.
Quick update for when this will be revisit in the future: Often we have contracts setting the response date as workining date as well, which become natural for admin setting up the system.
Unfortunately there are no plans to add this feature to Deliverables Management service at the moment.